| Opening: | Fall 2010 |
| Cost: | $380 million (total construction cost) |
| Location: | Downtown Orlando; bound by Church St. (north); Hughey Ave. (east); South St. (south); Division Ave. (west) |
| Owner: | City of Orlando |
| Developer: | Events Center Development, LLC |
| Operator: | Allen Johnson, City of Orlando |
| Primary Tenants: | Orlando Magic; Orlando Predators |
| Functions: | NBA and collegiate basketball, arena football, indoor soccer, concerts, hockey, circuses, stage shows, exhibitions |
| Design Architect: | HOK Sport |
| Local Architects: | C.T. Hsu + Associates; Baker Barrios Architects, Inc. |
| Construction Manager: | Hunt Construction Group in association with Rey Group, R.L. Burns, Inc., HZ Construction and Albu & Asscociates, Inc. |
| Program Manager: | Turner Construction Company |
| Site Acreage: | 8.75 acres |
| Number of Levels: | 7: Event Level; Founders Level; Disabled Seating Level; Main Concourse; Club Level; Terrace Level; Press Box Level |
| Square Footage: | 800,000 square feet |
| Seating Capacities: | 19,000 (center stage concert) |
| 16,000 (end stage concert) | |
| 18,500 (NBA) | |
| 20,000 (NCAA basketball) | |
| 17,200 (hockey/arena football) | |
| Premium Spaces: | 56 suites; 4 Chairman suites; 2 super suites; 4 party suites (suites distributed on two levels) |
| 1,428 club seats | |
| 328 loge seats | |
| Sustainable Design: | Sustainable building design will exist in various categories, including a sustainable site; water efficiency; energy optimization and atmosphere protection; materials and resource conservation; indoor environmental quality and health; and environmentally preferred operations and maintenance |
| MBE/WBE Participation: | Commitment to Blueprint; 31% for design phase |