Orlando Events Center - Project Timeline
Orlando Events Center Information
Fourth Quarter 2007
Complete Schematic Design Phase
Construction Manager Selected
First Quarter 2008
Complete Design Development Phase
Second Quarter 2008
Issue First Construction Document Package
Third Quarter 2008
Complete Construction Documents
Construction Begins
Third Quarter 2010
Complete Construction
Opening Event